Client: Legal & General
Contract Duration: 40 Weeks
Architect: Michael Sparks Associates
Project Manager: Canmoor Developments Ltd
This project consisted of the construction of a 36,000sqft terrace of four warehouse buildings including a mezzanine in each unit, fitted out to offices for each unit as well as external works.
The topography of the site was a challenge we had to overcome by introducing various retaining walls around the perimeter of the site as well as between two of the units due to a step in levels. Further to this, a complex underground drainage system design was developed to accommodate the Environment Agency’s strict requirements.
Working with a new, novated design team on a site adjacent to live businesses and an airport, we succeeded in delivering this project on time and to budget, overcoming various issues out of our control along the way.