Client: The Diageo Pension Trust
Project Manager: Quartz Project Services Ltd
Architect: PRC Architecture & Planning
Contract Duration: 22 months, including tenant decant durations
Description: This phased project on a live industrial estate involves the demolition of existing units for the construction of new units into which existing tenants relocate to allow continued demolition and reconstruction. It involves extensive utility reconfigurations including sub-station relocation whilst keeping existing units live.
“The infrastructure requirements on this project, in particular, their sequencing, partly due to working around live tenants required a forensic level of planning and coordination to ensure project success”
Troy Hunter – Director